PacketStream - Planned Maintenance for Electrical Facilities at the ICN03 – Maintenance details

Planned Maintenance for Electrical Facilities at the ICN03

Completed
Scheduled for October 11, 2025 at 9:00 PM – October 12, 2025 at 12:00 AM

Affects

Datacenters

Under maintenance from 9:00 PM to 12:00 AM

(KR) ICN03 - Seoul, Gasan

Under maintenance from 9:00 PM to 12:00 AM

Updates
  • Completed
    October 12, 2025 at 12:00 AM
    Completed
    October 12, 2025 at 12:00 AM
    Maintenance is now in progress
  • In progress
    October 11, 2025 at 9:00 PM
    In progress
    October 11, 2025 at 9:00 PM
    Maintenance is now in progress
  • Planned
    October 11, 2025 at 9:00 PM
    Planned
    October 11, 2025 at 9:00 PM

    ENG

    We plan to conduct a statutory inspection of the electrical facilities at the ICN03 data center.
    This inspection is a scheduled preventive maintenance activity and will not affect any services.

    Schedule

    • Work Details: Mandatory inspection of electrical facilities (ICN03)

    • Date & Time: Sunday, October 12, 2025, 06:00 – 09:00 KST

    • Impact: No service impact as UPS and generators will operate normally
      (During the inspection, general and freight EV will be unavailable)

    We kindly ask for your understanding and will do our best to minimize any inconvenience.

    KOR

    ICN03 데이터센터의 전기 설비 대한 법정설비점검을 진행할 예정입니다.
    이 점검은 계획된 예방 점검으로, 서비스에는 영향을 미치지 않습니다.

    작업 일정

    • 작업 내용: 전기 설비 법정설비 점검 (ICN03)

    • 작업 일시: 2025년 10월 12일(일) 오전 6시 ~ 오전 9시 (KST)

    • 작업 영향: UPS 및 발전기가 동작하여 서비스에 영향 없음
      (점검 중 일반 및 화물 EV 이용 불가)